Charging Pile Design Standards and Installation Details

Today, I’ve been invited to share with you a detailed guide to charging pile design standards and installation.

charging pile design standards

1. Charging Space Selection Principles

1) Electric vehicle parking spaces should preferably be located in centralized parking areas within parking lots.

2) Electric vehicle parking spaces in surface parking lots should be located in easily accessible areas, avoiding locations near main entrances/exits, public activity areas, and major traffic flows;

3) Electric vehicle parking spaces in underground parking lots should ideally be located on the ground floor, preferably on the first or second basement level, and should not be located on the third basement level or below;

4) The site should not be near areas with potential fire or explosion hazards. When adjacent to buildings with explosion or fire hazards, it should comply with the relevant provisions of the current national standard “Code for Design of Electrical Installations in Explosive Atmospheres” GB50058;

5) Electric vehicle charging parking spaces in surface parking lots should not be located in low-lying areas or areas prone to water accumulation;

6) For centralized electric vehicle parking spaces, existing parking management systems should be utilized comprehensively;

7) Charging areas in the basements of commercial complexes and office buildings should be equipped with parking and charging guidance systems, including entrance signage, road guidance signage, and parking and charging signage. Entrance signs should be placed near the main entrances and exits; parking and charging signs should be placed on the ground and above the parking spaces; the specific design of various signs should refer to the national standard “Graphic Design and Signage for Electric Vehicle Charging and Swapping Facilities” GB/T31525-2015.

charging station operation

2. Charging Pile Layout Principles

The design of electric vehicle charging facilities should adhere to the following principles:

1) The layout of electric vehicle charging infrastructure should not obstruct the normal passage of vehicles and pedestrians.

2) Electric vehicle charging infrastructure should be rationally laid out in conjunction with parking spaces to facilitate vehicle charging;

3) The minimum distance between electric vehicle charging infrastructure and electric vehicle parking spaces or buildings should meet the requirements for installation, electrical safety, operation, and maintenance;

4) The centerline of wall-mounted charging equipment should preferably be 1.5m above the ground.

5) When outdoor electric vehicle charging infrastructure is installed on the ground, the foundation of the charging equipment should be 0.2m above the ground level of the charging site. For parking spaces of 6 meters and above, the base foundation should be at least 0.2m larger than the length and width of the charging facility; the base foundation should preferably be a concrete foundation with pre-installed power distribution lines.

6) When considering charging facilities for multi-level parking spaces, a detailed design is required based on the specific conditions, and cable-mounted car charging piles are recommended.

7) The placement of charging interfaces should follow the principles of adapting to local conditions and saving space.

8) AC charging piles should preferably be located at the intersection of the two parking spaces on either side of the parking space, behind the direction of the parking stop; DC charging piles are recommended to be multi-charger type and should preferably be located in an open space behind the column; the charging pile located directly behind the parking space should meet the requirements of GB/T 51313-2018, “4.0.2.4 The distance between the charging equipment and the charging parking space, building (structure) should meet the requirements of safety, operation and maintenance; the net distance between the outer contour of the charging equipment and the edge of the charging parking space should not be less than 0.4m”.

3. Electrical System Requirements

1) The technical conditions of charging facilities should comply with current national and industry technical standards. The protection level of charging piles should be no less than IP32 indoors and no less than IP54 outdoors.

2) The calculated load of electric vehicle charging infrastructure in parking lots of newly built buildings should be included in the total transformer capacity, or a dedicated transformer should be reserved in the distribution room. A dedicated transformer should be installed when the charging facility is 250kW or above, or the transformer installation capacity is 160kVA or above.

3) The power distribution system of charging facilities should meet the following requirements:

  • Medium and low voltage power distribution systems should preferably use single busbars, single busbar sectionalized systems, or cable wiring. Low-voltage grounding systems should preferably use TN-S systems.
  • Low-voltage incoming and outgoing line switches and sectionalizing switches should preferably be circuit breakers.
  • Low-voltage incoming line circuit breakers should preferably have three-stage protection functions: instantaneous short circuit, short-delay short circuit, and long-delay short circuit, and also have a grounding protection function. Low-voltage incoming circuit breakers should be equipped with shunt trip devices.
  • Off-board chargers, monitoring devices, and important electrical equipment should preferably use a radial power supply. AC charging piles can use trunk-type or radial power supply. The power supply wiring of multiple AC charging piles should consider the three-phase balance of the power supply.
  • Low-voltage circuit breakers on the power supply side supplying AC charging piles should preferably have short-circuit protection and overload protection, and should also have a residual current protection function. The rated operating current of the residual current protection should not exceed 30mA, and the operating time should not exceed 0.1s; multiple charging devices should not share a low-voltage electrical appliance with a residual current protection function.
  • The distribution coefficient values for multiple 7kW AC charging piles in the parking lot are shown in the table below; the distribution demand coefficient Kx for multiple 30kW DC charging piles should preferably be 0.4~0.8; the distribution demand coefficient Kx for multiple 60kW DC charging piles should preferably be 0.2~0.7.

4) The design of the power distribution wiring system should meet the following requirements:

  • Lines supplying power to the charging device should preferably use copper conductors, cables should preferably be cross-linked polyethylene insulated, and wires should preferably be polyvinyl chloride insulated. When the lines are laid outdoors, the outer sheath should preferably be steel tape armored. If local authorities have special requirements, those requirements should be followed.
  • The cross-section of the main line should be selected based on the long-term goals, and the cross-section of the cable conductors should be determined based on the load calculation results of the electric vehicle charging infrastructure.
  • Indoor cable lines should preferably be laid in cable trays or conduits; outdoor cable lines should preferably be laid in cable trenches or buried in protective conduits. The protective conduits should meet the requirements for pressure resistance and environmental corrosion resistance.
  • Low-voltage three-phase circuits should preferably use five-core cables, and single-phase circuits should preferably use three-core wires; the cross-sectional area of the neutral conductor should be the same as that of the phase conductors.

5) Newly built parking lots should have low-voltage power supplies led to the vicinity of the charging parking area, and a distribution box should be installed. A cable path should preferably be reserved from the distribution box to the charging equipment, and the size of the circuit breaker should match the charging equipment.

6) Communication cables for charging facilities should be laid in separate conduits, preferably along the same path as power lines;

7) Electric vehicle charging infrastructure should adopt effective power quality management measures to minimize the impact on building power distribution systems and the public power grid.

8) Ground-mounted charging facilities are classified as Class III lightning protection buildings. If constructed jointly with other buildings, the lightning protection level should be determined by comprehensively considering the nature of the buildings and through calculation. Charging facilities should take measures to protect against direct lightning strikes, lightning surge intrusion, and lightning electromagnetic pulses, and a Class I surge protection device should be installed in the distribution box.

9)The working ground, protective ground, and lightning protection ground of outdoor charging facility electrical equipment should share a common grounding device, and the grounding resistance of the shared grounding device should not exceed 4Ω. When arranging grounding devices around the foundation or using steel reinforcement in concrete as down conductors, a hot-dip galvanized steel conductor should be led out at 0.8m-1m below the outdoor ground level as the external lead point of the artificial grounding body. Grouped charging piles adopt a TNS grounding system, with their PE lines connected at the same potential to the grounding device on the power supply side.

10) Regarding the requirement in GB/T 51313-2018 “Technical Standard for Distributed Charging Facilities for Electric Vehicles” that “charging facilities in newly built underground parking garages should be centrally located within the same fire compartment and separated by independent fire-resistant units, with a maximum allowable building area of 1000 square meters for each fire-resistant unit,” please consult your local design approval authority.

11) Charging pile load rating: Fast and slow charging facilities in residential communities, commercial complexes, office buildings, and hotels are all classified as Class III loads;

12) All charging pile equipment must be equipped with meters.

13) For fire safety considerations, high-capacity fast charging products should preferably be installed above ground.