For the new generation of DC charging piles produced by our Bluesky Energy Technology Co., Ltd., during the production testing phase, we need to configure key parameters of all charging piles and conduct charging tests.
The new system has many settings, but the four most critical are “System Settings,” “Meter Settings,” “Module Settings,” and “Connector Settings.”

The following are the settings for these four items:
1. System Settings
In this interface, we need to set the “Number of DC Connectors,” “Number of AC Connectors,” “Type of Connector 1,” “Type of Connector 2,” and “Type of Connector 3.” These parameters need to be set according to the actual type of charger.

From the screenshot, we can see that this charger has three connectors: one CCS1 connector (DC), one GBT connector (DC), and one AC.
2. Meter Settings
In this interface, we need to set the “Baud Rate”, “parity”, “Meter count”, “Meter Protocol”, “Connector 1 Meter Address”, and “Connector 2 Meter Address”.

From the screenshot, we can see that the charger’s power meter has a baud rate of 9600, uses even parity, and has 2 DC meters. The meter protocol is DJSD2699D, the meter address for DC connector 1 is “000000000001”, and the meter address for DC connector 2 is “000000000002”.
There is one AC meter, using the 645-2007 protocol, and its protocol is 226061730001.

3. Module Settings
In this interface, we need to set the “Baud Rate”, “Protocol”, “Type”, “Number count”, “Control Mode”, “Connector 1 Module group Power”, and “Connector 2 Module group Power”.

From the screenshot, we can see that the charger module has a baud rate of 125000, a protocol of INFY, a type of AC/DC, a module quantity of “4”, a control mode of “parallel operation”, and a power of 60kW for both connector 1 and connector 2 modules.

4. Connector Settings
4.1 Connector 1
For connector 1, the parameters we need to set are “Connector 1 Type”, “Maximum Voltage”, “Minimum Voltage”, “Maximum Current”, “Minimum Current”, “Maximum Power”, and “European Standard adapter Protocol”.

From the screenshot, we can see that connector 1 of this charger is of type CCS1, with a maximum voltage of 1000V, a minimum voltage of 220V, a maximum current of 200A (the maximum current depends on the connector’s performance; some connectors can output 250A), a minimum current of 5A, and a maximum power of 120kW (when only one connector is charging, in parallel mode, it can start all modules, thus achieving a full power output of 120kW). Currently, our company’s chargers use three types of European standard connector conversion boards: RNL, StartCharge, and BLUESKY. We can select the appropriate model based on the specific type being used.

4.2 Connector 2

Regarding connector 2, as seen in the screenshot, this charger’s connector 2 type is GBT, with a maximum voltage of 1000V, a minimum voltage of 220V, a maximum current of 200A (the maximum current depends on the connector’s performance; some connectors can output 250A), a minimum current of 5A, and a maximum power of 120kW (when only one connector is charging, in parallel mode, it can start all modules, thus achieving a full power output of 120kW). For the GBT connector, since it does not use a European standard conversion board, we can ignore the conversion board type selection.

4.3 Insulation Detection
For chargers with two DC connectors, the parameters we need to set are: “Baud Rate”, “parity”, “insulation monitoring guns count”, “Type”, “Protocol”, “Connector 1 Address Code”, and “Connector 2 Address Code.”
From the screenshot, we can see that the baud rate is 9600, the parity is no parity, the number of insulation detection connectors is 2, the type is dual insulation, the protocol is “GONGYUAN”, the address code of connector 1 is “A0”, and the address code of connector 2 is “A0”.